Upcoming Construction Work (August 3 & 4)

Room construction for the MRI Equipment Replacement project in Diagnostic Imaging (DI) is nearing completion.

Throughout the day on Wednesday, August 3, the new Siemens MRI magnet and related equipment will be delivered and offloaded outside of G-Door. The magnet will be brought into the MRI suite through an opening in the exterior wall that is adjacent to G-door, while some of the equipment will be uncrated and brought in through G-Door. Please avoid using G-Door unless necessary.

On Thursday August 4, from approximately 9:00 – 9:30 a.m., the new Siemens MRI chiller will be delivered and offloaded outside of G-Door. During this time the G-Door as well as the ambulance bay exit doors, both vehicular and pedestrian, will not be accessible.

On both days please adhere to all signage/caution tape that will be posted in this area by the contractor to delineate the construction zone. Do not enter the construction zone for any reason.

Thank you in advance for your cooperation.